Annual targets for surrenders through Work Studies by Zonal Railways for 2021-22

Adoption of uniform guidelines for procedures followed in Compassionate Ground Appointment

Annual targets for surrenders through Work Studies by Zonal Railways for the year 2021-22: Railway Board

GOVERNMENT OF INDIA/भारत सरकार
MINISTRY OF RAILWAYS /रेल मंंत्रालय
(RAILWAY BOARD)

No.2020/E8&R/2(8)/1

New Delhi, dated 20.05.2021

The General Managers,
All Zonal Railways

Sub: Annual targets for surrenders through Work Studies by Zonal Railways for the year 2021-22

1. In view of technological advancements in various fields of Railway working, including office working, few activities have become obsolete/reduced, whereas, role of few other activities is increasing. As such, there is need to study such activities and re-assess the staff requirements for these activities.

2. Accordingly, Zonal Railways to carry out the well established and scientific way of assessing the workload of said units/sub-units/categories through work studies.

3. The rationalization of manpower provision for various activities through work studies as above will enable the organization to surrender surplus posts identified from some of the activities and create the required posts from the money value generated for the other activities/areas, whose role has increased in the changed scenario. Accordingly, the targets for surrenders through work studies by Zonal Railways for the year 2021-22 have been approved by Board (CRB). The same is attached as annexure-I.

4. In terms of Para ‘C’ (item vii) of Board’s letter no. E(MPP)/2010/1/67 dated 28.10.2016, posts surrendered after identification by work study should not be taken to pool of surrendered posts by the Zonal Railways and their money value should be credited to the Vacancy Bank as per extant orders.

Kindly acknowledge the receipt and ensure compliance.

(Umesh Balonda)
Executive Director (E&R)
Railway Board

Annexure-I

Targets of Zonal Railways through work studies for the year 2021-22

S.No. Rlys Targets
1 CR 1400
2 ER 1300
3 ECR 400
4 ECoR 500
5 NR 2350
6 NCR 400
7 NER 750
8 NFR 650
9 NWR 600
10 SR 1300
11 SCR 900
12 SER 900
13 SECR 500
14 SWR 300
15 WR 900
16 WCR 300

 

Click here to view/download the pdf